Monday, August 14, 2017

Preparing for Final Layer of Asphalt Paving

Work Performed, July 31st to August 11th
·         Complete concrete curb & gutter installation
·         Installed concrete sidewalks and driveways
·         Graded roadway prior to paving first layers of asphalt
·         Paved first layer of asphalt pavement
·         Rough grading and topsoil installation behind sidewalks
·         Replaced asphalt driveways as needed.
·         Perform testing of water main system as required per Village requirements

Work Anticipated to be Performed, August 14th to August 18th  
·         Make repairs to water main system that were identified in testing
·         Make final adjustments to structures
·         Restore areas damaged to make needed repairs
·         Pave final layer of asphalt

Thank you to all the residents along the roadway that were without access a few weeks back due to the concrete work in front of your homes. Your patience and understanding was greatly appreciated.

The contractor has continued to grade and install topsoil in the areas of landscape restoration; however, the sod will not be installed until mid-September when growing conditions are more favorable.

The final testing of the water main did find a few area that contractor needs to repair. The contractor will be making these repairs and restoring any damaged areas prior to installing the final surface layer of asphalt. With the first layers of asphalt installed, the amount of dust was greatly reduced and a smooth driving surface was provided.

We are hopeful the majority of the construction work will be completed in the next 1-2 weeks with the exception of sod installation.