Complete concrete curb & gutter installation
·
Installed concrete sidewalks and driveways
·
Graded roadway prior to paving first layers of
asphalt
·
Paved first layer of asphalt pavement
·
Rough grading and topsoil installation behind
sidewalks
·
Replaced asphalt driveways as needed.
·
Perform testing of water main system as required
per Village requirements
Work Anticipated to be Performed, August 14th
to August 18th
·
Make repairs to water main system that were
identified in testing
·
Make final adjustments to structures
·
Restore areas damaged to make needed repairs
·
Pave final layer of asphalt
Thank you to all the residents along the roadway that were without
access a few weeks back due to the concrete work in front of your homes. Your
patience and understanding was greatly appreciated.
The contractor has continued to grade and install topsoil in
the areas of landscape restoration; however, the sod will not be installed
until mid-September when growing conditions are more favorable.
The final testing of the water main did find a few area that
contractor needs to repair. The contractor will be making these repairs and
restoring any damaged areas prior to installing the final surface layer of
asphalt. With the first layers of asphalt installed, the amount of dust was
greatly reduced and a smooth driving surface was provided.
We are hopeful the majority of the construction work will be
completed in the next 1-2 weeks with the exception of sod installation.