Friday, August 25, 2017

Asphalt Surface Paving Being Scheduled

Work Performed, August 21st to August 25th
·         Internal televising of storm sewer system
·         Identified areas in need of potential repair during internal televising.

 Work to be Performed:
·         Pave final layer of asphalt once repair locations are identified and ensure all underground utilities are functional. 
·         Sod Restoration, to be performed in mid-September when growing conditions are typically more favorable.

The Village is continuing to work with the contractor to schedule the final surface layer of asphalt pavement; however, we want to ensure all underground utilities are functional and don’t require additional excavation to repair prior to paving.