Friday, August 18, 2017

Final Layer of Asphalt Paving to be Scheduled

Work Performed, August 14th to August 18th  
·         Made repairs to water main system
·         Restored driveways and pavement damaged to make repairs
·         Final testing was performed and passed.
·         Adjusted structures to final grade
·         General site clean-up
·         Miscellaneous tasks prior to project close-out.

Work Anticipated to be Performed, August 21st to August 25th  
·         Pave final layer of asphalt
·         Sod Restoration, to be performed in mid-September when growing conditions are typically more favorable.

Asphalt paving was not performed as anticipated due rain and threat of rain on Thursday and Friday. We are anticipating the final asphalt layer will be paved next week. We will provide a notice of the paving schedule.