Made repairs to water main system
·
Restored driveways and pavement damaged to make
repairs
·
Final testing was performed and passed.
·
Adjusted structures to final grade
·
General site clean-up
·
Miscellaneous tasks prior to project close-out.
Work Anticipated to be Performed, August 21st
to August 25th
·
Pave final layer of asphalt
·
Sod Restoration, to be performed in
mid-September when growing conditions are typically more favorable.
Asphalt paving was not performed as anticipated due rain and
threat of rain on Thursday and Friday. We are anticipating the final asphalt
layer will be paved next week. We will provide a notice of the paving schedule.