Friday, September 8, 2017

Major Construction Completed!!! Final Blog Post

Work Performed, September 5th to September 8th   
·         Paved final layer of asphalt
·         Final walk-through of project with Village staff.
·         Made repairs as identified during final walk-through.

Work to be Performed:
·         Sod Restoration, to begin next week (September 11th)
·         Make any additional minor repairs as needed.

The project is nearly completed and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide resident surveys in the coming weeks for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.

Thanks again for all your patience and understanding throughout the construction project. We hope that you are happy with the improvements made.

If you have any questions or concerns, please feel free to contact Tim Schwister, Village Project Manager, at 847-904-4422.

Friday, September 1, 2017

All Underground Work now Completed. Asphalt Surface Paving being Scheduled.

Work Performed, August 28th to September 1st  
·         Excavated to ensure the existing pipe was intact due to concerns following internal televising

Work to be Performed:
·         Pave final layer of asphalt 
·         Sod Restoration, to be performed in mid-September when growing conditions are typically more favorable.

The Village is continuing to work with the contractor to schedule the final surface layer of asphalt pavement. All excavations are now completed and asphalt paving is being scheduled as soon as possible.