Removed existing concrete pavement
·
Completed roadway excavation and installation of
gravel base materials
·
Removed existing concrete sidewalk.
·
Removed existing driveway materials.
·
Poured concrete curb & gutter and sidewalk
Work Anticipated to be Performed, July 31st to
August 4th
·
Complete pouring concrete curb & gutter and
sidewalk
·
Rough grading of landscape behind concrete
sidewalk
·
Fine grading of gravel base materials
·
Pave first layers of asphalt pavement
·
Driveway restorations.
Sections of the concrete sidewalk will be skipped to allow
for access to each home during concrete curb & gutter and sidewalk
construction. This will allow you to step over the concrete curb & gutter
without needing to get over the new concrete sidewalk as well. The concrete can
be walked on the day after it is poured, but takes several days prior to
driving a vehicle over the new concrete.
Thank you for all your understanding as driveway access has
been restricted during concrete curb & gutter and sidewalk construction.
Please be assured the Village is committed to ensuring the work is completed as
quickly as possible and driveway access is restored as soon as possible. It is
anticipated that driveway access will be restored by Friday, August 4th.
Driveway access will be restored once the concrete is properly cured and the
first layers of asphalt pavement are installed.