Completed water service replacements
·
Made final connections to existing water main
·
Abandoned / removed existing fire hydrants and
valves no longer in service.
·
Began removing sidewalk in preparation for
roadway improvements.
Work Anticipated to be Performed, July 24th to
July 28th
·
Perform roadway excavation and installation of
gravel base.
The underground utility improvements (water main, storm
sewer, sanitary sewer) are now completed.
The next phase of construction will be the roadway reconstruction phase. This phase of construction will consists of removing the existing asphalt pavement, repairing any areas of the existing soil below the pavement that are failing, installing new aggregate base, new concrete curb & gutter, new concrete sidewalks, and asphalt pavement.
As the roadway construction phase has started, access to
Parkview Lane will be limited during working hours. As you have been dealing
with over the past several weeks, heavy construction equipment and number of
workers has made it very difficult to travel along Parkview Lane. Next week
during working hours, the contractor will be excavating the entire roadway
width to remove the existing pavement and perform the work associated with
reconstructing the roadway. We ask that you remove your vehicles prior to
working hours, then following work completing for the day, you will have access
to your driveways. During concrete curb & gutter and sidewalk
installation, driveway access will be restricted for approximately 7 to 10
days. The Village of Glenview will be hand-delivering letters with exact dates
of the driveway and travel restrictions as well as parking options, please be
on the look-out for these letters on your front door.
Thanks again for all your patience and understanding. There
have been several unforeseen delays, including inclement weather, that have
caused this project to last longer than anticipated. The Village and contractor
are committed to getting this project done as quickly as possible.