Completed water main testing and placed the new
water main into service.
·
Began replacing water services to individual
homes.
Work Anticipated to be Performed Next Week, July 17th
to July 21st
·
Complete water service replacement
·
Make final connections to existing water main
·
Potentially begin roadway improvements
It is anticipated the underground utility portion of the
project will be completed by the end of next week including new water main
installation, water service replacement, and storm sewer improvements. The next
phase of construction will be the roadway reconstruction phase. This phase of
construction will consists of removing the existing asphalt pavement, repairing
any areas of the existing soil below the pavement that are failing, installing
new aggregate base, new concrete curb & gutter, new concrete sidewalks, and
asphalt pavement.
During roadway construction, access to Parkview Lane will be
limited during working hours. As you have been dealing with over the past
several weeks, heavy construction equipment and work has made it very difficult
to travel along Parkview Lane. During working hours, the contractor will be
excavating the entire roadway width to remove the existing pavement and perform
the work associated with reconstructing the roadway. We ask that you remove
your vehicles prior to working hours, then following work completing for the
day, you will have access to your driveways. During concrete curb &
gutter installation, driveway access will be restricted for approximately 7 to
10 days. The Village of Glenview will be hand-delivering letters with exact
dates of the driveway and travel restrictions as well as parking options,
please be on the look-out for these letters on your front door.
Thanks again for all your patience and understanding as you
live with construction along your street.