Friday, July 14, 2017

Water Service Replacements On-Going. Roadway Improvements to Begin

Work Performed, July 10th to July 14th    
·         Completed water main testing and placed the new water main into service.
·         Began replacing water services to individual homes.

Work Anticipated to be Performed Next Week, July 17th to July 21st  
·         Complete water service replacement
·         Make final connections to existing water main
·         Potentially begin roadway improvements

It is anticipated the underground utility portion of the project will be completed by the end of next week including new water main installation, water service replacement, and storm sewer improvements. The next phase of construction will be the roadway reconstruction phase. This phase of construction will consists of removing the existing asphalt pavement, repairing any areas of the existing soil below the pavement that are failing, installing new aggregate base, new concrete curb & gutter, new concrete sidewalks, and asphalt pavement.

During roadway construction, access to Parkview Lane will be limited during working hours. As you have been dealing with over the past several weeks, heavy construction equipment and work has made it very difficult to travel along Parkview Lane. During working hours, the contractor will be excavating the entire roadway width to remove the existing pavement and perform the work associated with reconstructing the roadway. We ask that you remove your vehicles prior to working hours, then following work completing for the day, you will have access to your driveways.  During concrete curb & gutter installation, driveway access will be restricted for approximately 7 to 10 days. The Village of Glenview will be hand-delivering letters with exact dates of the driveway and travel restrictions as well as parking options, please be on the look-out for these letters on your front door.

Thanks again for all your patience and understanding as you live with construction along your street.