This blog will typically be updated once per week, usually
on Friday, detailing the work completed the previous weeks and work anticipated
to be completed the upcoming week. It will also include information regarding
the construction operations. We hope you find the posts useful and
informative. The Village of Glenview will also be delivering letters to
your front doors on occasion detailing specific information regarding water
shut-downs and driveway restrictions. Please be on the lookout for these letters.
Work completed, June 5th to June 9th
·
Construction layout
·
Miscellaneous work in preparation for
construction
·
Saw-cutting along construction limits
Work Anticipated to be performed, June 12th
to June 16th
·
Water Main installation starting at Colfax
Avenue and working south, starting on Wednesday or Thursday.
The Village will do everything possible to minimize the
inconveniences during construction, but unfortunately some are unavoidable.